technology
General
information about the semi-precast construction
method
Building with
partly precast Wall and Floor Elements
The semi-precast
construction method is based on the use of
partly precast wall and floor elements which
are made to measure in a precast concrete factory
and then supplied to the construction site. The
partly precast elements, containing the
reinforcement designed for the final structure,
provide the formwork for the in-situ concrete
poured at the job site. The partly precast
elements are erected at the job site using a
conventional crane, and after fixing some
additional reinforcement at the joints between
elements and at wall corners a complete storey
comprising the walls and the floor above will be
poured in one operation. The site-poured concrete
bonds together the various partly precast
elements to form a monolithic structure without
any joints.
Design
Considerations
Similar to
reinforced concrete frame construction, where
load bearing columns must be arranged one on top
of the other, the load bearing concrete walls in
the semi-precast construction method must be
arranged one on top of the other. The floors are
designed to act as a diaphragm which will
transfer wind loads to the vertical walls. The
load bearing walls will be rigidly connected one
to another by right-angle reinforced corners,
resulting in a very rigid and monolithic
structural system. The non-load bearing partition
walls and external walls may be individually
designed in accordance with local requirements.
Production
of the partly precast Elements
Nowadays it is
possible to pre-fabricate wall elements as well
as floor slabs completely automatic in precast
concrete factories. Integrated production systems
for floor slabs and wall elements use
multipurpose formwork panels, which are operated
in a closed circuit production line and on which
one may produce either the one-layer floor panels
or the two-layer wall panels in one compact
production unit.
In modern curcuit
production lines of this kind the operations of
placing reinforcement, casting concrete,
vibrating concrete and curing concrete always
take place at the same specially designed work
station. This increases productivity enormeously.
The formwork
panels will be automatically stacked on top of
each other in a curing chamber up to 14 pallets
in one pile. This way the heat resulting from the
curing process itself can be utilized. This
reduces the cost of energy.
CIM-Computer
lntegrated Manufacturing
In many factories,
the plate elements are already being produced by
the CIM-method. The design office first
computerises construction projects, using a
special software package (PC-standard). This
system first elaborates the detail plan of each
plate and the erection plan for the construction
site, then it works out the relevant production
data for steel and concrete. Via a master
computer, the entire factory - plotting,
reinforcing, concreting, curing - will be
controlled. Owing to this CIM-concept it is
possible to erect incividually designed buildings
just as economically as mass-produced building
units.
Handling and
Transport
Totally
prefabricated large-size concrete elements have a
very high weight and therefore need very strong
and expensive lifting devices and special road
vehicles. Partly precast elements, on the
contrary, can be handled by relatively light
portal cranes and the customary site cranes. Road
transportation can be effected by normal trucks.
The weight of the partly precast elements is only
about 25% (floor slabs) or about 50% (double-leaf
wall elements) in comparison with fully precast
elements. Therefore, the construction "area"
that can be shipped in one load is greatly
increased.
 |
Erection There is
little doubt that the joints in floors
and walls of buildings using fully
precast elements do create problems.
Experienced specialists may tackle the
problems, but ordinary construction
workers without special experience shy
away from these problems. Erecting the
partly precast elements is much easier:
The site-poured concrete connects all
elements in one continuous core without
any joints.
|
Time Factor
and Cost Advantages
The essential
advantage of the semi-precast construction method
results from the sensible distribution of
functions between the precast concrete works on
the one hand and the construction site on the
other hand. The complicated functions of
preparing formwork and placing reinforcement are
attributed to a well organized precast concrete
factory, whilst the bigger part of the heavy
concrete is poured at the job site.
The organizational
problems of the job site are thus enormeously
reduced.
Building with
the partly precast construction system means:
Erect elements - pour concrete finished.
An additional and
very important time and cost advantage of the
system is derived from the fact that both sides
of the wall elements and one side of the floor
elements are perfectly smooth and even.
Traditional rendering therefore is no longer
necessary - only the joints require filling in
and then the soffit may be "spray gunned"
with a plastic bonded paint.
Summary
The partly precast
construction system practically eliminates all
the problems that industrialized building has
suffered from so far.
The integrated
production method for partly precast wall and
floor elements has brought about the decisive
break-through in the industrialization of the
system by computer controlled, automated
production methods.
|